IN PROGRESS EXPERIMENTAL · AMATEUR-BUILT KIT SHIPPED · Q3 2024

Van's RV-14A

Kit #142104 · Lycoming IO-390 · Hartzell BA blended
Registration PENDING · reservation N814WW (pending FAA)
Build totals
Hours on build842.5 / ~1 900.0 est
A&P credit hrs412.0 (supervised)
Entries187 · 42 signed
Photos1284
§ 01 — Phase plan

Progress at a glance

PLANS REV D · UPDATED 2026-03-11
100%
Empennage
166.0 h
100%
Wings
248.0 h
100%
Fuselage
202.0 h
64%
Firewall fwd
98.0 / ~150.0
31%
Finishing
82.0 / ~260.0
4%
Avionics
8.0 / ~180.0
0%
Engine & run
0.0 / ~120.0

§ 02 — Build journal

Latest entries

2026-04-19 · SAT · 3.5 h logged

Torqued engine mount bolts & installed oil cooler

FIREWALL FWD A&P CREDIT · 3.5h PHOTOS · 7
Pulled the engine back out to clean up chips on the oil cooler bracket per KAI Section 46-08. Torqued all four mount bolts to 350 in-lb per Lycoming SSP-1776. Oil cooler installed with new AN815 fittings, checked for interference through full elevator travel — clear. Safety wired per 43.13-1B ¶ 7-130. Supervising A&P witnessed torque and safety wire pattern.
IMG_1847.dng
engine mount — torqued
IMG_1852.dng
oil cooler bracket
IMG_1858.dng
safety wire — final
Supervising A&P signoff
V. Sterling
Sterling, Vera T. · A&P/IA 2189443 · DAR 7744
sha256:5c78 e1a4 3bf0
anchored: OTS 2026-04-19
2026-04-14 · MON · 5.0 h logged

Baffle fabrication complete — both sides fitted

FIREWALL FWD A&P CREDIT · 5.0h PHOTOS · 12
Baffles cut, trimmed, drilled, dimpled, primed. Left side fit on first try, right side needed about 3/16" trimmed off the aft rib ramp to clear the inter-cylinder fin. Rubber seal material (Van's part U-708) glued in place with 3M Super 77. Left overnight to cure before installing air filter snorkel.
IMG_1802
L-side trimmed
IMG_1809
R-side dry-fit
IMG_1814
seal glue-up
IMG_1821
primed & done
2026-04-11 · FRI · 2.0 h logged · DRAFT

Ordered exhaust system · Vetterman crossover

FIREWALL FWD DRAFT — not yet signed

Ordered Vetterman crossover exhaust with heat muff, tailpipes, and slip joints. PO VE-26-8814. ETA 6 weeks. Will pause engine installation until exhaust arrives to avoid multiple fits.

2026-04-06 · SUN · 4.5 h logged

Engine hung — Lycoming IO-390 S/N L-34821-48A

FIREWALL FWD MILESTONE A&P CREDIT · 4.5h PHOTOS · 18
Engine out of crate, preserved per Lycoming SL-180B, hoisted via the prop flange fixture. Hung with four rubber biscuits and dynafocal mounting bolts torqued and safety-wired. This registers the engine S/N as a first-class component on the airframe graph — its hour tracking will begin at first engine start.